Project Overview:
Overview Client: J. Murphy & Sons
Duration: 13 months (March 2022 – June 2023)
Project Description and Scope:
The Sellindge Sub Station project involved the reinstatement of a fire-damaged sub-station in Sellindge, Kent. The scope was extensive and included both the restoration of existing structures and the enhancement of the facility’s functionality and aesthetic appeal. The project required meticulous attention to detail and a commitment to quality, given the historic and functional importance of the sub-station.
Brick and Blockwork Restoration:
Challenges and Solutions:
Outcome and Impact:
The Sellindge Sub Station project was a significant success, despite encountering numerous challenges due to design and access changes. Nevertheless, the reinstatement and upgrades not only restored the sub-station to its former glory but also ensured it met contemporary standards for functionality and safety. The project demonstrated ASH Construction Group's commitment to quality, client satisfaction, and the ability to handle complex, large-scale projects.
© ASH Construction Group Ltd 2013-2025 - All Rights Reserved
| Privacy Policy
Website by